From July 2015, Cost Solutions Co., Ltd has officially become Exclusive Agent of DEG - Dal Engineering Group - a Turkish Corporation with more than 30 years of operation experience in providing Turnkey solutions for cement, ore and power plants as well as automation industry.
Currently , Cost Solutions is providing FONS COOLER from DEG and also installation support - with the outstanding features:
- Total time of installation and back to operation: maximum of 02 weeks
- European standard quality, but the price can compete with coolers from China, because the product is new in the market
- No trough fall of clinker, reduced building height
- Low energy consumption (fuel and electrical)
- Operating: 1,94-2,33 kg_air/kg_clinker (1,5-1,8 Nm3/kg)
- Design: 2,56 kg_air/kg_clinker (1,98 Nm3/kg)(+10%)
- Guarantee: Clnker (65deg+amb)
Standard cooler loss: 95kCal/kg => 79% efficiency
4,5 kWh/t (fans); 0,3 kWh/t (hydr.)
- 0,002 Euro/t (10% of others)
- Grate line: no more wear part, 3 yeas guarantee